Approach Roads,Streets & Lanes

Summary of projects undertaken for this year 2012 / 2013 –

 

  • Main features

 

  •  
    1. There is a plan to spend over €320k by the town council on road and footpath repairs in 2013. Much of the work will be carried out in Estates. All the locations have been prioritized and comes under the heading of Carriage way Restoration.

 

  •  
    1. The Westmeath County Council with the funding from the NRA have re-aligned the three Junctions
    2. ( J9, J10 & J11) over the Town Bypass. This included the installation of traffic lights and a new pedestrian Bridge at Garrycastle. In conjunction with this exercise, in March this year, they carried out a major litter pick and hedge and grass margin improvement thus making the bypass cleaner and more user friendly.

 

  •  
    1. The new crossing over the Railway at Garrycastle commenced in March 2013 and will take 18 months to complete. This is a major project and will remove one of the most dangerous bridges over the railway in and around Athlone.

 

  •  
    1. The John Mc Cormack monument frontage has been renewed to be in harmony with the adjoining Luan Gallery.

 

  •  
    1. Our workers augment the work of the Town Council to curtail the spread of annual weeds throughout the town. This is regarded as vital to improve the appearance of the town.

 

  •  
    1. All back lanes have been visited and cleared of rubbish. In particular, we cleared out what is locally called Lowry Lane in April this year.  However new rubbish may appear from time to time which will need attention.

 

  •  
    1. The roadway at the Big Meadow area is prone to dumping and has been cleared up in May 2013.

 

  •  
    1. Grass verges on the Old Dublin Road and the Ballymahon Road have been edges and re-seeded where requires.

 

  •  
    1. Power washing has taken place at Pearse Street, The Strand, The Bawn, Civic Centre and the tunnel at Coosan area

 

  •  
    1. Bridge at Battery Heights power washed and railings painted in May 2013.

 

  •  
    1. Large roundabout at Ballymahon Road at the Regional Sports centre was power washed in May 2013. The Civic Centre Plaza was cleaned and all seats painted in May this year.

 

  •  
    1. Signage clutter at the top of Northgate/Custume Place removed as recommended by Donaldson report.

 

  •  
    1. Willow Park received great attention to address neglect.

 

  • General plan is to improve the approach Roads of the town.

 

Ballymahon Road from the Mullingar turnoff straight into town at the White Gates.

This is nearly completed with only a few more grass verges to attend to. Major work was carried out across from Colm Quinn’s Garage and the grass verge between there and the Cornamaddy roundabout. We carried out much trimming and repairs last summer to enhance this main access road into the town as we see it as the first point of making an impression to our visitors.

Kilmartins Roundabout to Town Centre. This is a very long stretch and difficult to manage with the AIT located on it. However, we are happy that much remedial work has been carried out in the last year and it is fairly presentable. There is a stretch opposite Woodies that need attention and this is subject to resources being available. Some hoardings are spoiling the appearance of the road and we are dealing with this problem with the owners.

Roscommon Road to Town Centre. This stretches from Ganlys Roundabout and includes the Old Roscommon Road. This road has been given a lot of attention. The problem is slightly complicated as the Roscommon County Council is responsible for part of it. However, they normally make a contribution towards the planting of flowers in that part of town. Towards the town centre we have carried out a lot of work last Summer and it is in good shape.

Baylough to the start of Roscommon Road. This is in need of attention and could do with renewal and further planting in order to soften its appearance. . It will be addressed subject to the resources at our disposal.